An Extra Set of Expert Eyes: How One Damaged Pothead Boot Nearly Cost a Motor
A damaged pothead boot caught before running in hole — why half a day of rig time beats a short run, rig remobilization, and tens of thousands in avoidable costs.
A Recipe for Disaster
This example highlights the importance of having an additional set of expert eyes on ESP installations.
During this new installation, several setbacks occurred, including issues with the delivered equipment, kinks in the capillary string, and difficulties hanging the sheaves. When you're behind schedule, the temptation to rush can lead to mistakes. Combine that with early call-out times, and you have a recipe for disaster.
The Damaged Pothead Boot
The attached picture shows a damaged pothead boot, which seals the MLE connection to the motor and prevents water infiltration. During the connection, a small portion of the boot between the motor and MLE did not seat properly and was damaged.
Fortunately, this was noticed before the motor was run into the hole and exposed to wellbore fluid. Unfortunately... a new motor was needed after the Monel bolts seized, compromising the integrity of the pothead connection.
What If It Had Been Run?
Had this motor been run, how long do you think it would have lasted? In the best case, it might have produced for a short period. In the worst case, it could have grounded before reaching bottom.
Either way, it's better to incur an additional half day of rig time to get it right than to risk a short run and have to start over from scratch.
The Economics
The former would incur rig DEMOB costs, startup costs, additional down production costs, and rig MOB costs again versus 12 hours of NPT for the rig. Estimations are in the tens of thousands — and a lot of heartache!